Post-construction view under the MRHA plans: the Warehouse removed

Help us save the Warehouse

We’re afraid we have some very troubling news and we need your help. Under the Midlands Rail Hub Alliance (MRHA) Bordesley Chords consultation plans, the Warehouse is currently proposed for demolition around 2030.

UPDATE: SEPTEMBER 2026

Thank you for all your support. The MRHA consultation is now closed and we’re really grateful to everyone who filled it in. We very much hope that the overwhelming response to the consultation sends the message to the MRHA that they need to come up with a plan to improve railway infrastructure that does not destroy or damage large parts of the Digbeth cultural landscape. While we’re waiting to hear what the outcomes are from the consultation our Board are considering how we would respond to the various options they might put forward and we’ll continue updating everyone as and when we can.

 

The situation

What the plans show, and our engagement with MRHA

The proposals are at an early stage and the developers still have options to vary the scheme. We need to take this opportunity to show them they should.

MRHA propose to extend the viaduct that crosses Allison Street by 15 metres north widthways, which takes it to midway through the cottage. They plan to demolish the rest of the building and garden to make room for a “worksite” for construction plant, access and materials.

We support the aims and objectives of the wider rail improvements, but the more we look, the more we conclude this particular design has severe impacts not just on our building but on the entire economy and built heritage of Digbeth. We want MRHA to explore other options that would reduce land acquisition and construction that is both costly and environmentally damaging. This would not only save our building but much of the economy, nature space and built heritage of Digbeth, and be much better value for money for the public purse. You can see the current plans here (PDF).

We have met with MRHA and made them aware of the five decades of volunteering and financial investment that have created the intrinsic value of our building for the city, and our keenness to work with them on solutions, just so long as our future is secure.

MRHA have assured us that they are at an early stage and willing to explore other options.

Why it matters

This building is not just BFOE’s ‘property’. It’s the result of five decades and millions of volunteer-hours of activism and commitment from BFOE, other residents and guests, steadily building its social outcomes, condition and business success. It’s the city’s heart of activism, an irreplaceable city-centre meeting space for hundreds of community organisations every year, and a building in which we have in the last year invested over £100K in new roofs and energy efficiency measures. It has expanded into a beautiful wildlife garden, a rare Digbeth green space. And much more. No financial compensation can make up for this loss.

So we need them to reconsider their land requirements and work with us.

A bit more information

You can read all the consultation materials on the MRHA site. The consultation closed on August 28, 2026.

In summary: the proposals in full are intended to add extra capacity to the rail network serving and passing through Birmingham, reducing the capacity constraints at New Street by developing more rail infrastructure at and through Moor Street.

Timescale would be construction 2030 to 2034 at the earliest. There will also have to be a Transport and Works Act Order, which could involve a public inquiry. Any Compulsory Purchase Order (CPO) would not be until 2029 to 2030 at the earliest.

Press and background briefing. Journalists and anyone wanting the full background can download our briefing: Word version | PDF version. This briefing may be updated as the situation develops.

New to the Warehouse? The Warehouse is the home of Birmingham’s environmental and social movement. Find out more about the building and everything that happens there. Visit the Warehouse website (opens in a new tab).

Save the Warehouse

Latest updates

A (Weary) Climate Activist’s Guide To The Galaxy

In the middle of what is –once again- shaping up to be the hottest summer on record, the [...]

Protect The Warehouse Open Day 22nd August

So much news to update people with! Thanks to everyone who has got stuck in to the campaign, [...]

Further information – how to respond to the Bordesley Chords consultation

Some people have been asking us for a bit more info on how they can respond to the [...]

See all Save the Warehouse updates